Improving On-Time Delivery in a Metalworking SME Using Demand-Driven MRP and Simulation-Based Validation

Producción científica: Libro o Capítulo del libro Contribución a la conferenciarevisión exhaustiva

Resumen

Peruvian metalworking SMEs struggle to meet the 87.5 % on‑time delivery (OTD) benchmark, largely because existing material requirements planning systems fail under intermittent demand. This study closed that gap by integrating Demand‑Driven Material Requirements Planning (DDMRP) with Croston‑based forecasting and validating the approach through discrete‑event simulation. After mapping the current value stream, strategic inventory buffers were dimensioned from a 31‑month demand series for chassis tanks and embedded in an Arena model of the line. Compared with the baseline, the proposed system raised simulated OTD from 41.6 % to 94.0 % and cut average production lead time from 55.4 to 18.3 days, delivering an estimated annual net profit of US $73,894 against an investment of US $4,533. The work provides the first quantitative evidence of DDMRP’s effectiveness in the Peruvian metal‑mechanic sector, demonstrates its transferability to settings with high demand variability, and contributes a replicable procedure for practitioners seeking sustainable, low‑capital performance gains.

Idioma originalInglés estadounidense
Título de la publicación alojada2025 11th International Conference on Innovation and Trends in Engineering, CONIITI 2025 - Conference Proceedings
EditorialInstitute of Electrical and Electronics Engineers Inc.
Edición2025
ISBN (versión digital)9798331591328
DOI
EstadoIndizado - 2025
Publicado de forma externa
Evento11th International Conference on Innovation and Trends in Engineering, CONIITI 2025 - Bogota, Colombia
Duración: 1 oct. 20253 oct. 2025

Conferencia

Conferencia11th International Conference on Innovation and Trends in Engineering, CONIITI 2025
País/TerritorioColombia
CiudadBogota
Período1/10/253/10/25

Nota bibliográfica

Publisher Copyright:
©2025 IEEE.

Huella

Profundice en los temas de investigación de 'Improving On-Time Delivery in a Metalworking SME Using Demand-Driven MRP and Simulation-Based Validation'. En conjunto forman una huella única.

Citar esto